Texas Resumes Data Center Environmental Permit Reviews

The Texas Commission on Environmental Quality (TCEQ) has resumed standard environmental permit reviews for data centers after a pause initiated in September by Governor Greg Abbott. The pause was to allow the Electric Reliability Council of Texas (ERCOT) to assess the impact of data center projects on the state's grid, water, and communities. ERCOT has gathered data from 93% of 465 projects, but its final report is still pending. The resumption of reviews suggests a shift back towards normal regulatory operations, potentially decreasing the likelihood of a formal moratorium on data center construction. Watch for the release of ERCOT's final community-impact report, which is targeted for December 10. This report could either reinforce the current trend away from a moratorium or introduce new considerations that might shift sentiment.