Crusoe Orders 13 Gas Turbines for AI Data Centers
AI infrastructure firm Crusoe has ordered 13 gas turbine generator sets from ProEnergy to power its upcoming hyperscale data center projects. The contract covers 13 of ProEnergy’s PE6000 units, each rated at 50 MW, adding 650 MW of generating capacity. The turbines are expected to arrive by summer 2027, with factory testing and quality checks taking place at ProEnergy’s facility in Sedalia, Missouri.